DLP – Managing the Forgotten Project Stage

by Aug 27, 2020

The post-handover of construction projects is often called the warranty or defects liability period (DLP).

The defects liability period or post practical completion stage is too often the forgotten stage of the work.  The focus is on contract completion, handover, and critical project payments that can overshadow the final stage of the project.  For many, the Warranty or DLP stage is treated as a 12 month period to finish unfinished work of defects.

Part of the problem is that the scope of services is hidden in the specifications for each trade and that each consultant responsible for the specification holds their own subjective view on the scope and responsibility for delivery

For example, the Mechanical Services Specification can include replacement of the construction filters with new filters during the DLP term plus the regular preventive maintenance for the next 12 months.  Other examples can be Landscaping, where the first 3 months includes mowing and weeding, watering and for the remaining 9 months services are limited to replacement of dead plants only.

The exact scope can be subject to clauses in the specification like ‘undertake all required routine services in accord with manufactures or statutory requirements.  In effect, the exact scope is yet to be defined until the Operations and Maintenance Manuals have been completed.

Added to this is the risk to longer-term product warranties where the owner cannot verify that proper servicing of the equipment has been undertaken.

So how can the DLP term be improved?

Here are some quick points to consider when managing the final project stage.

  1. Check the all the trade specifications for hidden post-handover or DLP requirements especially those where some form of regular servicing is required
  2. Develop a schedule for each affected sub-contractor and seek their confirmation on the exact services to be delivered over the DLP
  3. Confirm with the owner the scope of servicing and the role of an in-house or incumbent maintenance providers
  4. Confirm the statutory services that are required and review the O&M Manuals to ensure the scope is covered
  5. Create a logbook system and ensure sub-contractors complete each service and provide the right documents to verify the works

The OmTrak Siteworks Module is designed to manage the DLP. It enables builders, subcontractors, and clients to produce and review O&M Manuals online. With a simple flick of a switch, the maintenance schedules within the O&M Manuals can be activated for OmTrak’s Site Works App. Once the scheduled servicing is on, each sub-contractor will receive regular work notifications via email. They can then record the details of the service with supporting photos and documents.  The system produces ongoing status reports and upon completion a logbook for handover to the client.

Contact OmTrak to find out how we can help.

OmTrak Siteworks Defects and Punchlists

Above: OmTrak Siteworks Module, onsite maintenance schedule during the defects and liability period.

Reduce costs & time delays.

Our products have been developed by industry experts and refined over the last twenty years to ensure high quality project outcomes. Our consulting services provide additional support for those that just need a little extra help.